Explore our 1500L craft beer project in Gunsan, South Korea – featuring a 4-vessel brewhouse, fermentation tanks, BBTs, bottling and kegging systems. Delivered by SDET with expert engineering and turnkey support.

Project timeline:
First communication: March 2024
Project completion: February 2025
Equipment list:
1500L 4-vessel Brewhouse;
3000L * 4 fermentation tanks, 1500L * 10 fermentation tanks;
3000L * 1 BBT, 1500L * 2 BBT;
Semi-auto bottling and keg filling equipment;
PLC control system;
Process pipeline;
100L Portable CIP.



Project progress:
Process and solution confirmation: 100 days (based on customer’s project planning)
Contract Finalization & Equipment Specification: 20 days
Manufacturing & Production: 70 days
Installation and commissioning: 30 days
Manpower Allocation: 1 SDET engineer, 2 on-site assistants supported by the buyer
This project showcases SDET’s turnkey brewing solution — from design and engineering to production and on-site support — ensuring smooth operations and long-term value for our client in South Korea’s growing craft beer industry.