Turnkey Solution for Rice Wine Project

SDET successfully delivered a complete 1200L rice wine brewing solution tailored to meet the traditional brewing practices of Korea, while integrating modern process efficiency and hygiene standards.
Project Scope & Equipment Supplied
1. Rice Processing Equipment:
- Rice Steamer
- Overhead Crane
- 200L × 2 Rice Steeping Tanks
2. Fermentation & Storage System:
- 1200L × 4 Fermentation Tanks
- 1200L × 2 Post-Fermentation Storage Tanks
- 1200L Buffer Tank
- 300L High-Level Tank
3. Filtration & Pasteurization:
- Filter Press
- Flash Pasteurizer
- Bag Filter
4. Packaging & Cleaning:
- Semi-Automatic Glass Bottle Filling Line
- 100L Portable CIP Unit
- Full Set of Sanitary Process Pipelines
Project Timeline & Execution
- Client Communication Initiated: March 2024
- Process Flow & Solution Design: 130 days
- Contract & Technical Specifications Finalization: 20 days
- Equipment Manufacturing: 70 days
- On-site Installation & Commissioning: 30 days
- Project Completion: March 2025
Manpower Deployed:
- 1 SDET Brewing Engineer
- 2 Local Assistants (provided by buyer)