We’re excited to share a successful brewery installation! This 1000L craft beer project is tailored for a high-end hotel in Gyeonggi-do, bringing premium craft brewing capabilities to its premises.

Project Timeline:
First communication: September 2023
Completion: December 2024
Equipment list:
Grist hopper, grinding and conveying equipment;
1000L 5-vessel Brewhouse;
2000L * 2 Hot & Cold water tanks;
1000L * 5 fermentation tanks;
1000L * 2 BBT;
100L Portable CIP;
Refrigeration system;
PLC control system;
Steam supply system;
Keg cleaning and filling equipment, etc.




Project progress:
Process and solution confirmation: 150 days (based on customer’s project planning)
Contract Finalization & Equipment Specification: 20 days
Manufacturing & Production: 60 days
Installation and commissioning: 25 days
On-Site Support: 1 SDET engineer, 2 on-site assistants supported by the buyer.
This turnkey brewing solution ensures high efficiency, quality, and consistency—perfect for elevating the craft beer experience at the hotel.